Can your carton stock absorb a supplier delay?
Work through a carton reorder decision with a late receipt. Use both inventory position and day-by-day stock to see when a new order will arrive too late.
| New order scenario | Demand per operating day | Usable receipt lead time | Reorder point | Position above or below point |
|---|---|---|---|---|
| Normal demand, standard lead time | 120 cartons | 6 days | 960 cartons | +80 cartons |
| Normal demand, longer lead time | 120 cartons | 9 days | 1,320 cartons | −280 cartons |
| Peak demand, longer lead time | 150 cartons | 9 days | 1,590 cartons | −550 cartons |
Build a daily demand baseline
In this constructed scenario, four five-day weeks used 575, 610, 590 and 625 cartons of one stock code. The 2,400 cartons issued over 20 operating days give an average of 120 cartons a day. Count replacements and damaged cartons when they draw from the same stock. Use the same operating calendar for lead time, from order release to usable inventory after receiving and inspection. Record the reason for excluding an abnormal issue or one-time promotion.
Compare the stock position with each trigger
Usable on-hand stock is 710 cartons. An open purchase order is expected to supply 480, and 110 cartons are allocated to existing jobs with another 40 backordered. The position is 710 + 480 − 110 − 40 = 1,040. Keep the 150 commitments separate from the forecast of new demand in this example so neither is deducted twice. Each reorder point is daily demand × usable lead time + 240 reserve. Extending lead time from six to nine days adds 360 cartons to the trigger at normal demand even though today's stock has not changed.
Check the date the open order will actually help
The net usable quantity before receiving the 480 cartons is 560. At 120 cartons a day it covers four full days and 80 of the 120 cartons needed on day five. An accepted receipt on day three avoids that near-term gap. If the receipt comes after the close of day six, planned demand exceeds available stock by 40 at the end of day five and by 160 at the end of day six. Check delivery time, inspection capacity and any stock on hold. Arrange an earlier partial receipt or verify an approved substitute when the normal reorder cannot arrive before the gap.
Set the order quantity and record the exception
In the nine-day lead-time case with the scheduled receipt still expected, the 1,040-carton position is below the 1,320-carton trigger. If your order-up-to target is 1,800 and stock comes in cases of 100, round the 760-carton gap up to 800. The resulting position of 1,840 includes stock on order, so check the receiving forecast separately. The 240-carton reserve is an assumption in this example. Review it against demand swings, actual usable receipt times, storage space and the frequency of your inventory checks.